How to calculate Soil filling cost
How to calculate soil quantity for land filing in the plot?
This is the first step for everyone, whoever start building his home or construction. To start construction ,we all need to fill land ,above road level to get a proper elevation.
So that's the first calculative problem occurs behind us,that how much soil we need to fill the land properly to get the proper level.
Many of us , deal with soil filling dealer and some of us buy soil as per trolly rate.
But that things do not give us a proper calculation of soil filling.
So how to calculate soil quantity ?
Let me know you...
Plot size length ? Breadth? Depth?
Length x breadthxdepth = volume of soil needed
Let's take
Length =50 ft breadth=30ft depth=4ft
50x30x4=6000cu.ft soil needed
How much tractor trolley it takes to fill?
Trolly size 12ft x6ftx2.5ft =180 cu.ft
So total no. Of trolly needed= 6000/180
=33.33 no. Of trolly
Rate of 1 trolly= 2000rs ( as per our area rates)
So total cost = 34x2000rs
= 68000rs
You have to deal with any soil filling contractor to fill soil below this amount . So you will get good deal above this amount you will be is in loss.
So next time before dealing with any soil filling contractor, calculat it first then ,deal it with a contractor.